DOW JONES NEWSWIRES The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list. ExxonMobil (XOM) Thursday reduced feed to a deasphalting unit at its Baytown, Texas, refinery owing to the shutdown of the associated J-1 compressor, a filing to state environmental regulators said. The compressor is expected to restart Friday at about 3:40 p.m. CDT. Motiva (RDSA, RDSB) Friday began five days of repairs at a delayed coker unit's jet pump; the unit will continue to operate, perhaps at reduced rates, while an alternate pump will be used for three hours every seven hours, a filing to regulators said. Tesoro (TSO) will restart a hydrocracker unit at is Los Angeles area refinery Friday, after shutting down, unplanned on Thursday, a person familiar with operations at the plant said Thursday. The company reported an unplanned breakdown of equipment Thursday to California state environmental regulators. Royal Dutch Shell (RDSA, RDSB) on Tuesday said a catalytic reformer unit at its Puget Sound refinery in Anacortes, Washington, will be restarted on June 28 after going off-line on June 19 when a fire broke during the shutdown process of an associated heater shut to fix a small leak. The unit is expected to resume normal processing rates by June 30, the company said. Valero Energy Corp. (VLO) Monday said that a coker unit at its Benicia, California, refinery was shut over the June 19-20 weekend for unplanned maintenance following two reportable emission events on Thursday. There is not restart estimate. Valero Energy Corp. said Monday that planned maintenance got underway over the June 19-20 weekend to de-coke a coker unit at complex 7 of the east plant section of its Corpus Christi, Texas, refinery. That work will last several days. For more detailed information, search Dow Jones Newswires using the code N/REF. Operator Refinery Capacity Description Restart (in 000s bbl/day) UNPLANNED GULF COAST Exxon Baytown 562.0 Feed to deasphalting unit re- Jun 25 TX duced early on June 24 to facilitate compressor repairs. Compressor to restart June 25. Lyondell Houston 268.0 CDU hit by fire on May 17 is Jun 20 TX expected to restart in four weeks. 2nd crude unit re- started from unplanned mainte- nance on May 19. All other pro- cess units have been operating with feedstocks on hand. Motiva Port Arthur 285.0 Delayed coker unit jet pump Jun 30 TX shut for 5-days of repair June 25; unit will continue to operate. Work to conclude June 30. Valero Sunray, TX 170.0 FCCU upset when expander coup- mid-Jul ling on power train failed June 16. The unit could be down until mid-July, the co. said on June 17. MIDWEST BP Toledo, OH 125.5 FCCU expected to resume operations June 17 after going offline June 15 due to a boiler failure, a person familiar with operations. ROCKIES Sinclair Casper, 20.0 Refinery running at reduced rates Wyo. after explosion, co said. May 27 WEST COAST Chevron El Segundo 279.0 Isomax plant shut March 19 n/a CA due to "small" fire. No estimate on restart. Conoco Carson, CA 139.0 Company reports flaring due to an exceedance in sulfur dioxide emission. Event noted as "non- emergency; cause unclear. Conoco Ferndale, 100.0 An alkylation unit and butamer n/a WA following a pump fire early June 15, an environmental agency said. The refinery continues to operate, Co. said June 15. Shell Anacortes 145.0 Catalytic Reformer Unit seen at Jun 28 WA normal rates by June 30; unit shut following brief fire on June 19. Tesoro Wilmington 100.0 Hydrocracker Unit will restart Jun 25 CA June 25 after shutting down un- planned on June 24, a source said. The company reported an un- planned equipment failure on 6/24 to state regulators. Tesoro Anacortes 120.0 Fire at naphtha unit April 2 end Q2 WA killed seven. Plant will be shut until Sept at least, the co. said June 11. Valero Benicia, CA 177.0 Coker Unit shut June 19-20 for No Est. unplanned maintenance. PLANNED CANADA Shell Montreal 130.0 The refinery could be converted Quebec into a fuel terminal but Co. said its in talks with 2 potential buyers. CARIBBEAN Valero Aruba 235.0 Idled refinery to restart in 90 days after completing turnaround, Co. said June 7. Valero continues to evaluate options for the plant. Tax dispute resolved. EAST COAST Sunoco Westville 145.0 Idling all Eagle Point refin- n/a NJ ing operations indefinitely due to poor economics, Co. said Oct. 6. Valero Delaware 210.0 PBF Investments has closed Apr 2012 deal to buy plant. Petroplus said May 5 the plant would be restarted in 2Q of 2011. Valero Paulsboro 185.0 Small crude unit restarted Jun 19-20 NJ June 19-20; unit shut June 6 to facilitate maintenance at reformer and hydrotreater. Western Yorktown 64.5 Planned work scheduled 3Q 2010. Q3 2010 VA GULF COAST Conoco Borger, TX 146.0 Maintenance activity to take place at several units June 5- July 22, with emissions from units including FCC, GOHDS, SCOT unit incinerator, SRU incinerator and units 41, 42, 45 and 98. Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010 Miss. conversion project delayed from 2008 to 2010 due to economic factors. Work is progressing on the continuous catalytic reformer, expected to be completed by mid-2010, Co. said Feb. 25. Co. is planning to put a premium base-oil facility at plant. Flint Corpus $250 mln project for new Spring 2010 Hills Christi, TX diesel desulfurization, sulfur recovery unit to begin in Fall 2008. Construction to last 18 months. Motiva Port Arthur 285.0 Repairs on DCU pump June 8-13. TX Expansion project to increase 1Q throughput capacity by 325,000 2012 b/d, to 610,000-b/d, slowed. Completion now seen 1Q 2012, from 2010. Valero Corpus 340.0 West Plant 50,000-b/d FCCU at Christi, TX reduced rates since mid-Dec for economic reasons. Planned maintenance to de-coke Jun 25 coker unit in complex 7, east (est.) plant will last several days; unit shut. Valero Norco, LA 250.0 Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to 4Q 2012. Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a TX rates since mid-Dec for economic reasons. Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a rates since mid-Dec for economic reasons. Expanded crude gather system 4Q will increase available crude 2010 supplies to refinery by 4Q. (MORE TO FOLLOW) Dow Jones Newswires June 25, 2010 08:46 ET (12:46 GMT)